Progress!
The foundation is totally completed and the block wall has been installed. The contractor has this job running like a well oiled machine. As soon as one phase is completed, the next day they are working on the next phase.
Read MoreWe are a couple of days behind schedule.
Thanks to all the rain we had last week we are a couple of days behind schedule. The guys have been working overtime to catch up and keep the job moving. As of today we are done pouring concrete and the foundation has been completed.
Read MoreThe area for the new foundation has been dug out.
Despite what you may hear, no we did not find Jimmy Hoffa. The foundation guys were at the club for over 12 hours digging getting ready to pour concrete. The weather held up just enough today to start pouring the footing. Everything is coming along as planed and there have been no surprises. We hope to have the foundation completed by the end of next week. See a picture of the footing being poured and a $20 bill being placed in the footing for luck.